TL;DR
  • SAP PM transactional objects span five phases — Measurement Management, Notification Management, Work Order Management, Work Execution, and Settlement — with eight objects connecting condition monitoring through to cost settlement.
  • The dependency order is strict: Measurement Document → Maintenance Notification → Work Order → Order Operation / Order Component → Goods Movement → Confirmation → Order Settlement. Maintenance Plans can auto-generate Notifications without a prior Measurement Document.
  • Each end-to-end maintenance scenario (Condition-Based, Preventive, Corrective, Emergency) is covered in detail in PM-B02 onward.

1) Transaction Process Flow

SAP PM Transaction Process Flow — Phase 1 Measurement Management, Phase 2 Notification Management, Phase 3 Work Order Management, Phase 4 Work Execution, Phase 5 Settlement

2) Hierarchy Structure

SAP PM Transaction hierarchy — parent-child relationships across measurement, notification, work order, execution, and settlement phases

3) ER Diagram

SAP PM Transaction ER diagram — cardinality between all eight transactional objects

4) Transaction Process

PhaseObjectIntegrationPlannedActualPrerequisiteTr-CdDescriptionPractical ExamplesRole
1 Measurement ManagementMeasurement Document---Measuring PointIK11/IK12Record equipment measurement data and monitor thresholdsRecord vibration value 0.5mm/s; threshold exceeded triggers auto notificationMaintenance Technician
2 Notification ManagementMaintenance Notification-Maintenance NotificationMaintenance Plan (*1)Equipment, Functional Location, Maintenance PlanIW21/IW22/IW23Register maintenance request or breakdown report; select notification typeCreate M1 notification for equipment breakdownMaintenance Planner
3 Work Order ManagementWork OrderCOWork OrderMaintenance NotificationMaintenance Notification, Task ListIW31/IW32/IW33Plan and manage maintenance work; select order typeCreate PM01 order for preventive maintenanceMaintenance Planner
Order Operation-Order Operation-Work Order, Task ListIW32Define individual operations within the work order; set work timeRegister 2-hour inspection operation and 1-hour replacement operationMaintenance Planner
Order ComponentMMOrder Component-Work Order, BOMIW32Define parts required for maintenance work; set quantitiesRegister 2 bearings and 1L of oilMaintenance Planner
4 Work ExecutionGoods MovementMM/FI-Order ComponentOrder ComponentMIGORecord parts issue and return; use movement type 261Issue 2 bearings to maintenance work orderWarehouse Clerk
ConfirmationCO-Order OperationOrder OperationIW41/IW42Record work completion and actual labor hoursEnter 2.5 hours actual time for inspection operationMaintenance Technician
5 SettlementOrder SettlementCO/FI-Work OrderWork Order (TECO)KO88Transfer maintenance costs to settlement receiver; allocate to cost centerSettle 500,000 JPY maintenance cost to cost centerCost Accountant

(*1) Maintenance Plan is Master Data and is not covered in this document. See PM-A01 and PM-A07 for details.


L1) Big Picture

IDCategoryTitle
pm-001OverviewWhat is SAP PM?

L2-A) Master Data

IDCategoryTitle
pm-a01OverviewSAP PM Master Data: Overview, Hierarchy & Relationships
pm-a02-01Master DataSAP PM Functional Location
pm-a02-02Master DataSAP PM Equipment
pm-a03-01Master DataSAP PM Class
pm-a03-02Master DataSAP PM Characteristic
pm-a04-01Master DataSAP PM Measuring Point
pm-a05-01Master DataSAP PM Work Center
pm-a06-01Master DataSAP PM Material Master
pm-a05-02Master DataSAP PM Task List
pm-a05-03Master DataSAP PM Production Resource Tool
pm-a06-03Master DataSAP PM Maintenance BOM
pm-a07-01Master DataSAP PM Maintenance Item
pm-a07-02Master DataSAP PM Maintenance Plan

L2-B) Transaction

IDCategoryTitle
pm-b01OverviewSAP PM Transactions: Process Flow, Hierarchy & Relationships 📍