A structured knowledge base for SAP S/4HANA Project System.

L1) Big Picture

IDCategoryTitle
PS-001OverviewWhat is SAP PS

L2) Functional Domains

A) Master Data

IDPhaseCategoryObjectScope
PS-A01—OverviewMaster DataSet up Flow / Hierarchy / ER / Process
PS-A02-01MaterialMaterial MasterMaterial Master
PS-A03-01Phase 1ProfileProject ProfileProject Profile
PS-A03-02Network ProfileNetwork Profile
PS-A03-03Milestone GroupMilestone Group
PS-A04-01Phase 2Project StructureProject DefinitionProject Definition
PS-A04-02WBS ElementWBS Element
PS-A04-03WBS Element (AuC)WBS Element for Assets under Construction
PS-A04-04WBS HierarchyWBS Hierarchy
PS-A05-01Phase 3NetworkNetworkNetwork
PS-A05-02ActivityActivity
PS-A05-03Activity ElementActivity Element
PS-A05-04MilestoneMilestone

B) Transaction

IDCategoryProcessScope
PS-B01OverviewTransaction FlowProcess Flow / Hierarchy / ER / Process
PS-B02PlanningProject Planning ProcessScheduling→Capacity Planning→MRP→Cost/Revenue Planning
PS-B03BudgetBudget Management ProcessOriginal Budget→Budget Release→Availability Control
PS-B04ExecutionWork Execution ProcessTime Recording (CATS)→Activity Confirmation→Forecast Dates
PS-B05ProcurementProcurement ProcessPurchase Requisition→PO→Goods Receipt→Invoice Verification
PS-B06MaterialMaterial Consumption ProcessMaterial Reservation→Goods Issue
PS-B07BillingMilestone Billing ProcessMilestone Confirmation→Sales Order→Billing Document→Revenue Posting
PS-B08Resource-Related Billing ProcessResource-Related Billing→Sales Order→Billing Document→Revenue Posting
PS-B09ClosingPeriod-End Closing ProcessOverhead Calculation→Interest→Results Analysis→Project Settlement
PS-B10CompletionProject Completion ProcessTECO→Final Settlement→Project Close
PS-B11InvestmentInvestment Project ProcessWBS Element [AuC]→Project Execution→Settlement→Fixed Asset